Integrating digital displays into new construction is straightforward. But embedding high-definition LED screens into a fully finished, high-traffic heritage site without altering the existing structure — that requires engineering. The Johnny Cash Museum asked DOIT VISION to transform a central 12-step wooden staircase into a dynamic digital canvas. Using value engineering with standard 320×160mm COB modules, ultra-slim aluminum profiles, and impact-resistant epoxy encapsulation, the entire system was designed, manufactured, and delivered in just 15 days.

Project Scope
12 Steps
P1.8 COB · 320×160mm Modules
Pixel Pitch
P1.8
COB · 5H Hardness
Timeline
15 Days
Production → Dispatch
Total Width
1,920mm
6 Modules × 320mm
Delivered by DOIT VISION Engineering Team · · Reviewed by Kris Liang, Co-Founder · August 2026
CE · EMC · RoHS
15 Engineers · 60-Person Shenzhen Team
55+ Countries · NovaStar · Colorlight
Contour PCB + FlexibleMooncell + ResolumePoka-Yoke Assembly
Project Overview

At a Glance

Client
Johnny Cash Museum
Heritage Site · Tennessee
Location
Tennessee, USA
On-site retrofit
Display Technology
P1.8 COB LED
5H hardness · Epoxy sealed
Module Format
320×160mm Standard
Zero custom PCBs
Structure
Ultra-Slim Aluminum
Front-serviceable magnetic
Key Challenge
No Structural Alteration
Fully finished heritage site
Mounting
Screw-Mount from Behind
Direct into wooden structure
Support
Remote Pixel Mapping
12 risers as one canvas
01 — Dimensional Constraints

The Strict Dimensional Constraints

The client provided the exact, unchangeable dimensions of the existing staircase:

  • Total Steps12 risers
  • Riser Height5 7/8" (approx. 150mm)
  • Riser Width11 steps at 77.5" (1968.5mm) + 1 bottom step at 61" (1549.4mm)

The dilemma was clear. Standard LED cabinets are bulky — usually 500×500mm or 1000×250mm — which would completely ruin the depth of the stairs or protrude past the rounded lips of the wooden treads. Custom-sized PCB boards for a relatively small 12-step project would skyrocket R&D costs and blow the museum's budget.

02 — Value Engineering

Standard Modules, Custom Results

Instead of reinventing the wheel with expensive custom circuit boards, our engineering team looked at the client's dimensions and immediately identified a mathematical synergy with our standard mass-produced modules.

Strategic Sourcing

We selected our standard 320×160mm P1.8 COB LED modules. The 160mm module height was a near-perfect fit for the 150mm exposed riser height, maximizing visual area without a single custom PCB. By placing 6 modules horizontally (320mm × 6), we achieved an exact width of 1920mm — perfectly centered within the 1968.5mm stair width with a clean, symmetrical margin on both sides.

This value engineering approach — using standard modules creatively instead of designing bespoke PCBs — saved the museum tens of thousands in custom fabrication costs while keeping the 15-day delivery timeline achievable.

03 — Structural Engineering

Ultra-Slim Profile Design & Wiring

We engineered custom ultra-slim aluminum profile cabinets measuring exactly 1920×160mm — rigid backbones that added minimal depth to the existing stairs.

  • Direct Screw-MountingBecause the stairs were wood, the local crew simply drove screws from behind the stairs directly into the aluminum frames — no messy brackets, no structural alteration.
  • 100% Front-ServiceableCOB modules attach via heavy-duty magnets. If a module ever needs replacement, a technician pulls it off from the front with a suction tool — no disassembly required.
  • Hidden InfrastructureAll power supplies and receiving cards were routed behind the hollow wooden stair structure, keeping the face of the stairs completely clean.
04 — 15-Day Delivery

From Shenzhen to Tennessee in 15 Days

By heavily utilizing standard 320×160mm COB modules rather than drafting custom PCBs, we slashed the production timeline drastically. The complete 12-step system was manufactured, tested, and dispatched in just 15 days.

Upon arrival in Tennessee, the client's local crew handled the physical mounting smoothly thanks to the plug-and-play design. DOIT VISION's support team then stepped in via remote video link to map the 12 separate risers in software, digitally stacking them so that when the museum plays a video, content cascades seamlessly up and down the stairs as a single unified canvas.

Key Engineering Insight

True engineering mastery isn't always about building the most complex custom circuit board. Often, it's about having the intelligence to use standard, highly reliable components in creative ways to solve strict physical constraints, respect budgets, and crush delivery deadlines.

05 — Material Science

Why COB is Mandatory for Stair Displays

Specifying the right LED packaging technology is the difference between an installation lasting 5 years or 5 days. For any display installed at foot level, SMD is a liability.

The Vulnerability of SMD

Standard SMD (Surface-Mounted Device) screens consist of millions of tiny LED bulbs soldered onto a board. A single accidental kick from a shoe shears off multiple diodes, resulting in permanent dead pixels — unacceptable in a premium museum environment.

The COB Armor

COB (Chip-on-Board) directly bonds the LED chips to the PCB, which is then completely coated and sealed in hardened epoxy resin. This creates a flat, smooth surface with 5H Hardness rating — highly resistant to scratches, kicks, and direct impacts. Because the surface is sealed, it's inherently water-resistant, meaning museum staff can safely wipe down and clean the stairs without damaging internal electronics.

By the Numbers

Project Specs

12
Steps
11 wide + 1 narrow bottom step
1.8
Millimeter Pixel Pitch
COB · 5H hardness impact-resistant
320×160
Standard Module Size
6 modules per riser = 1920mm width
150
Riser Height (mm)
Near-perfect fit with 160mm module
15
Day Delivery
Production to dispatch
0
Custom PCBs
100% standard module value engineering
How We Delivered

15-Day Retrofit Process

Stage 01

Dimensional Capture

Fixed dimensions verified: 150mm risers, 1968.5mm / 1549.4mm widths. Value engineering identified 320×160mm module synergy.

Stage 02

Aluminum Profile Fab

Custom 1920×160mm ultra-slim aluminum profiles fabricated with rear screw-mounting points and magnetic module interface.

Stage 03

Production & Dispatch

12 complete COB stair assemblies manufactured, tested, and dispatched in 15 days. All power and data pre-routed.

Stage 04

Remote Pixel Mapping

Local crew handled physical mounting. DOIT VISION engineers mapped 12 risers remotely — content cascades as one unified canvas.

Planning a retrofit installation?

Don't demolish your existing architecture just to fit standard LED cabinets. Our engineering team uses ultra-slim profiles and standard module synergy to save you thousands in custom fabrication costs.

Talk to an Engineer →
Buyer's Questions

Frequently Asked Questions

Can LED displays be installed on existing staircases without demolition?
Yes. For the Johnny Cash Museum, DOIT VISION engineered ultra-slim aluminum profiles that screw-mounted directly to the existing wooden stairs from behind — no structural alteration, no demolition. All power and control hardware was routed through the hollow stair structure, keeping the installation completely hidden from view.
Why is COB mandatory for stair and floor LED applications?
COB (Chip-on-Board) encapsulates LEDs in hardened epoxy resin with 5H hardness. This armor layer withstands kicks, scuffs, and shoe impacts that would instantly shear off exposed SMD diodes. The sealed epoxy surface is also water-resistant, allowing safe cleaning without damaging internal electronics. For any display installed at foot level, COB is the only viable technology.
What's the advantage of using standard modules over custom PCBs?
Using standard 320×160mm modules instead of custom PCBs dramatically cuts costs and lead times. At the Johnny Cash Museum, the 150mm riser height was a near-perfect fit for the 160mm module height — eliminating an estimated $15,000–25,000 in custom PCB R&D. It also compressed the timeline from 6–8 weeks to just 15 days, since standard modules are in continuous mass production.
How do you map content across multiple stair risers as one canvas?
Each riser is treated as an independent display tile. DOIT VISION engineers map all risers in the LED controller software as a single logical canvas — digitally stacking them so video content cascades seamlessly from the top step to the bottom as if it were one large screen. This mapping can be done remotely via video link, as was done for the Tennessee installation.
How fast can DOIT VISION deliver a stair LED retrofit?
The Johnny Cash Museum's 12-step system was manufactured, tested, and dispatched in 15 days using standard 320×160mm COB modules. Typical lead times range from 2–4 weeks depending on step count and whether custom cabinet dimensions are required. We pre-assemble and pre-wire all assemblies before shipping to minimize on-site installation time.
Is front maintenance possible on stair LED installations?
Yes. DOIT VISION designed the aluminum profiles with magnetic front-serviceable COB modules. If any module needs replacement, a technician simply uses a suction tool to pull it off from the front — no need to access the rear of the stairs. This is critical for installations where the back of the stair structure is inaccessible after installation.

Your Custom Shape, Engineered

Send drawings or a rough diameter/height sketch — we will assess whether a flexible solution alone works. Reply within 48 hours.

WhatsApp an Engineer Get a Quote View All Case Studies
Manufacturer
DOIT VISION
Author
Kris Liang, Co-Founder & Lead Engineer
Author Experience
19 years LED display engineering
Content Type
Case Study
Primary Topic
P1.8 COB LED Stairs Retrofit — Johnny Cash Museum, Tennessee
Key Technologies
COB LED, P1.8mm, 320×160mm Standard Module, Ultra-Slim Aluminum Profile, Front-Serviceable Magnetic Mounting
Project Scope
12 steps
Pixel Pitch
P1.8 COB
Client Location
Tennessee, USA
Timeline
15 days from production to dispatch
Date Published
April 2026
Date Reviewed
August 2026
Certifications
CE, FCC, RoHS, CB, ISO 9001
Countries Served
55+
Founded
2013, Shenzhen, China
In-House Engineers
15
Get in touch
Start your project.
We respond same day.
Send your room dimensions, pixel pitch requirements, or project brief — an engineer replies within hours.
Same-day engineer response  ·  CE · EMC· RoHS
Manufacturer
DOIT VISION
Founded
2013, Shenzhen, China
Headquarters
Shenzhen, Guangdong, China
Certifications
CE, FCC, RoHS, CB, ISO 9001
Official Website
https://www.doitvision.com/